Liquor was, in fact, distilled on the plantation. It was simply part of life during the 18th century. Crops were grown for the table, livestock raised, and goods produced… be it clothing, furniture, or shoes. Just imagine the possibilities of having a carpenter or blacksmith on site with the skills to custom design interior and exterior features for the property. This was, obviously, long before shopping malls or the Internet! Additionally, the Lees had access to the Potomac River and the world beyond where ships were capable of making deliveries from Europe.
Wednesday, April 11, 2012
Still Exciting
Liquor was, in fact, distilled on the plantation. It was simply part of life during the 18th century. Crops were grown for the table, livestock raised, and goods produced… be it clothing, furniture, or shoes. Just imagine the possibilities of having a carpenter or blacksmith on site with the skills to custom design interior and exterior features for the property. This was, obviously, long before shopping malls or the Internet! Additionally, the Lees had access to the Potomac River and the world beyond where ships were capable of making deliveries from Europe.
Wednesday, March 21, 2012
Preservation and Restoration Excitement... No Really...
As sprin
g arrives a little early here at Stratford Hall, I am preparing for the warmer weather. The first thing I did to prepare for spring, with the help of the Collections Department, was to install the bird nets on the doors of the outbuildings. We install these nets to keep the pesky barn swallows out of the historic buildings but still allow our visitors access. You can read more about our issues with these birds here.Also as spring arrives the department is currently lookin
g for its annual summer intern. So far we have a great applicant pool and it will soon be time to make the hard decision of who gets to spend 10 fun-filled weeks at Stratford Hall. If you are interested in knowing more about our internships the posting can be found on our website.I am also gearing up to begin working on the exterior of some of the historic structures again. This work will consist of wrapping up the Slave Quarter restoration and continuing to work on the Great House windows. I am sure I will be getting into some more projects as the season progresses, so check back.
Monday, December 5, 2011
Update from the Preservation Department
After extensive investigation and research, the evidence to direct us in the restoration of the Parlor has been found. One item that will be done is the removal of the window seats (see image left) from the window embrasures. The window embrasures will then extend to the floor and contain paneling that will match the existing Federal Period wainscoting (see image below). The next major change will be the installation of a plaster cornice. The exact design of the 1790's cornice is not known, but the original dimensions have been determined. The architects are currently researching
other cornices from the same time period in Virginia to help guide them in their design. The paint scheme will also change during the restoration. Through paint analysis it has been determined that the walls will be a yellow-green verdigris while the wainscoting and wood work will be a cream color. These are the biggest changes you will see during the Parlor's restoration.Another recent project for the Preservation Department is the completion of a Historic Structure Report, also known as a HSR, on the Great House. This report presents an overview of the Great House's physical history from the time it was built by Thomas Lee up until the early restorations of the 1930's. This report was prepared for Stratford Hall by Mesick Cohen Wilson Baker Architects, LLP. The report pulls together years of research along with new research and investigations, and has been an essential guide in the ongoing restoration of Stratford Hall. As we proceed with the room projects, more research and investigation will be added to the HSR. Information from this document will also be incorporated into our tours of the Great House.
Friday, August 12, 2011
What Liz has been up to...
As this summer’s Building Preservation/Restoration Intern, I had the wonderful opportunity to work on some of the many historic structures at Stratford Hall and to gain hands-on skill and knowledge under the tutelage of Director of Preservation Phil Mark. Over the past ten weeks, I got to try my hand at masonry, wood repair, glazing and of course (everyone’s favorite) scraping, sanding and painting at the Slave Quarters, the Great House and in the workshop.
My main project, however, was the repair of the Great House second floor windows. Working on a scaffold fifteen feet in the air, I set about giving each 32-pane window some much-needed TLC. I assessed the level of failure of glazing putty and paint, removed and replaced failed putty, scraped failed paint, sanded, primed and painted each window.
Occasionally I encountered some more advanced damage than cracked putty and peeling paint, like I did on window 220. The sill on 220 had a patch of spongy, rotten wood which, when removed, revealed a baseball-sized void.
The hole in the sill of window 220
Following Phil’s sage advice, I began to repair this hole (and several large checks emanating from it) with a three step process. First the hole and checks were treated with a termiticide, insecticide and fungicide concentrate to stave off further decay. Next, a two-step liquid epoxy resin was applied to consolidate and seal the checks and interior of the void.
Finally, I used a two-step epoxy putty to fill the voids in the sill.
Once the putty hardened, it was sanded down the level of the sill around it….
…and primed and painted with the rest of the sill.
The result may not knock your socks off—in fact, from the ground you may not notice any difference at all. Someone once told me that when preservation work is done well, no one knows you’ve been there at all. I can only hope that in time, the work I’ve done this summer helps the windows of the great house last another few hundred years—or at least until Phil can convince another intern to climb up there...
This summer has been a wonderful learning experience in an idyllic place with some of the nicest people I’ve ever met, and although it was probably the hottest summer I can remember, it was also one of the best.
Best wishes from Stratford Hall,
Liz Christian
Building Preservation/Restoration Intern, Summer 2011
Friday, January 28, 2011
Cold Weather and Winter Projects
Winter is definitely upon on us here at Stratford Hall. Punxsutawney Phil may have predicted an early spring, but we will not be packing up our cold weather clothes anytime soon!
Stratford Hall maintains reduced hours in the months of January and February, so many of you might be wondering what we do in the winter. The truth is that we do not even notice a difference! There is always a lot of work to be done, so these months allow us to focus on projects that are difficult to complete during our busier seasons. One example is the current repair of the south door of the Great House. The Interpretation and Education Department keeps busy in the winter even when there are far fewer visitors. Policies need to be updated, reports collated, visitation data analyzed, work spaces organized, and exhibits repaired. A new newsletter was produced for local schools about the educational programs and new outreach plans created to attract more group tours. It is not exciting work, but sets the groundwork for a successful and productive 2011.
The 2011 Cal
Stay tuned for more updates about all the work that has happened the last few months.
Tuesday, October 26, 2010
The new Slave Quarters Exhibit
The exhibits in the West Slave Quarters have been updated and are now open to the public. If you would like a refresher on all our activities this summer, please read our posts about Restoration of the Slave Quarters and Furnishing Plan for the Slave Quarters.
The first pieces to
go into the new spaces were the new barriers. Andrew and Eric from AK Metal Fabricators spent two days at Stratford Hall to install our new barriers. The design is the same as those used in the Southwest Outbuilding. These barriers will protect the collection, allow visitors a clear view of the exhibit, and stand-up to the elements. They also pivot open, making cleaning and maintenance very easy.
Our next component was the new text panels. Neal and Doug from Gropen spent a day installing text panels and reader-rails (text panels that sit on top of our barriers).The last installation was the archaeological samples. Built-in to our new reader-rails are archaeological boxes. These plexi-glass boxes contain archaeological finds that were discovered around the Slave Quarters and provide insight into the lives of the slaves who lived here. The final step was for Curator Gretchen Goodell and Collections Manager Sarah Holland to move the artifacts and furniture into the new exhibits.
Below are some more images of the finished exhibit. Next week we will highlight the new Hand-on Activity Room.

Thursday, September 16, 2010
So that is what the scaffolding is for...

The layers of paint are being removed using infrared heat and scrapers. Once the paint is removed, any required preservation of the wood can be done. The entire cornice will then be primed and repainted. This is a very labor intensive project that will continue throughout the fall and continue in the spring (work will stop for the winter months).
While you may not notice a huge difference the next time you visit us, this type of work is an integral part of the preservation of Stratford Hall.
Thursday, July 29, 2010
Investigating the House...
Prior to their arrival, we opened multiple probe areas throughout the first floor so they could see what evidence might be behind the plaster. Other physical evidence they examined and scrutinized included nail holes, wear patterns on the floors, scars and patches in the wood work, and wall framing that could be observed from the attic. We are waiting for the team to analyze their finds before we share too much, but I can share one or two discoveries. One question we think we answered is that the unique niches in the East and West Passages appear to be original with a little reworking by "Light Horse Harry" Lee. One other discovery we were not expecting is that the evidence points to a closet being present in the back section of the Nursery that would have been accessible from the adjoining Chamber.
Thursday, July 1, 2010
Summer Preservation Interns at Stratford Hall
The interns of the preservation department, under the supervision of Phil Mark, are commencing work on their summer restoration project. Erin White, a graduate student from the Heritage Resources program at Northwestern State University in Natchitoches, Louisiana, started the ten-week internship at the end of May. Jess Warren, from Georgia, is a student in the building preservation technology program at Belmont Technical College in St. Clairsville, Ohio, and he started his internship in mid-June.
This is what they have to say:
Our main project for the summer is the restoration of the reconstructed slave quarters near the Great House. Before Jess’ arrival, Phil and Erin started by removing the back window sashes on the east quarters. The sashes were labeled and taken back to the preservation shop. Using environmentally-friendly silent paint remover, which uses infrared heat, Phil and Erin began removing the glaze, glazing points, and paint from the exterior side of the sashes. We then removed the panes of glass, taking much care not to break them. After all of the glass was removed, the interior sides of the sashes were sanded.
Jess cut the Restoration Glass to replace the broken panes. Restoration Glass is cylinder glass made in Germany in the manner of early glass production before the invention of float glass in the 20th century. Restoration Glass is appropriate to the period of the main house. After the panes were checked to ensure a proper fit, Jess used Sarco glazing to set the glass, which requires a very steady hand.
Currently, we are removing paint and sanding the eaves and window frames of the quarters. We then use Boracare, a non-toxic insecticide, to protect the wood. After this dries, primer, then paint, is applied. If you come by the slave quarters and see us on scaffolding, this is probably what we are doing, so feel free to ask any questions. We’re there Monday through Friday, 9:00-5:00!
Friday, June 25, 2010
Update from the Preservation Department

Friday, April 2, 2010
Traditional Hand Ground Paint in the Stair Passage
This paint was made by Erica Sanchez Goodwillie of Clinton, NY. Erica also spent a week here at Stratford Hall applying this special paint with the help of Jack Fisher of Plains, VA. The hand ground paint was made by hand grinding the pigments in the linseed oil. The pure pigments were then mixed with more linseed oil until a color match was achieved. At this point more linseed oil and chalk were added to extend the paint. Then, when it comes to applying the paint, it is a completely different beast than modern paint. When applying the paint you must be sure all surfaces are properly prepared or the paint will "flash," which means the paint loses its appropriate gloss. You must also be sure not to apply the paint too thick or it will wrinkle. These are only a couple of the differences between hand ground paint and paint we use today.

Wednesday, January 27, 2010
Directional Update from the Preservation Department...
outhwest Outbuilding, two of the three rooms are about 90% complete. In the w
orkshop space I began to finish the cleaning and conservation of the chimney breast. I am continuing where the conservator left off so he can return to finish conservation of the horse mural. This cleaning and conservation consists of picking off the remaining paint with a scalpel and then washing the wall with distilled water and cotton. My intern, Abby Muse, helped me one day and the two of had so much fun it was difficult to contain ourselves...
west Stair Passage is also progressing. There have been a few recent snags, but nothing major. Every day, the spaces begin to look more and more like rooms again. The plaster contractor, Cooke's of Richmond, Va, has been hard at
work plastering the spaces. They are almost finished with the lower level and will be moving to the Main Floor space next week. They have been very cooperative and respectful while working in the Great House. Our other contractor, Chuck Rackley, is getting closer and closer to wrapping his work up. He was here this week installing some beautiful door architraves that he made. His assistant, Billy, has
also been a great help on the project. Next week we will be bringing in a ladder stair that Chuck and Billy made for access to the attic. When the ladder stair is in the room, the plasterers will be able to close everything up and finish the plaster work. Decisions on paint color have been made but I will save that for a future post, so stay tuned!Monday, November 30, 2009
Northwest Stair Passage Update


Thursday, May 7, 2009
More finds in the Northwest Stair Passage
to support the restoration of the stair passage. The picture to the right shows the ground floor room of the Northwest Stair Passage before I began removing plaster and with the mock-up in place. The fragments that we have can also be seen in the mock-up. Just the other day I carried out over three quarters of a ton of plaster in bags from the Great House. I have identified some interesting and exciting things in the past few weeks. The most exciting (to me at least) is what I believe to be areas of plaster that are contemporary to Light Horse Harry’s stair passage. One area of plaster that would have been in the closet appears to have never received a finish coat of plaster. I believe this because the scratch coat appears to have been white washed. This white washed scratch coat was found under a layer of Portland-based
plaster from the 1930s restoration. It appears that this type of original plaster also exists in the transition area between the ground floor and main floor in the stair passage opening. This discovery of 18th-century plaster gives me hope that other plaster escaped the earlier restorations and will be found throughout the Great House. The picture to the left shows the original plaster that was found on the south wall and some of the plaster and lathe that was removed.When removing the floor boards of the main floor room, I also found a number of architectural fragments. Under the Parlor wall, on what would be the ceiling of the ground floor room, I found what is believed to be an original piece of chair railing
. Other finds include wrought nails of different types--mainly lathe nails--a possible fragment of original plaster, and what appears to be a chandelier drop that remains undated. In the near future, the original plaster, chair rail fragment, and plaster fragments will have their paint analyzed to help date them and hopefully provide information in regards to the Northwest Stair Passage’s original finish types and colors.Friday, May 1, 2009
This Place Matters...
This picture was taken to kick off Stratford Hall's celebration of Preservation Month, which begins today. Many of our staff members are included in this photo, including the Executive Director, members of the Board of Directors, senior staff, interpreters, grounds keepers, housekeepers, volunteers, maintenance staff, and administrative staff. I think it is safe to say that everyone in this picture thinks of Stratford Hall as a special place and works hard to make sure it will be here for generations to come. We hope that you will take time this month and pitch in to help preserve a place that matters to you. No place is too small and every single one matters to our country's cultural heritage.
Stratford Hall will also be celebrating Preservation Month with an event on May 16th. Please come help us celebrate this important month and this historic site!
Monday, March 23, 2009
The Answers Seem to Raise More Questions
The investigation has included paint analysis, archival research, and the work of
multiple architectural historians, preservationists, and architects over the past 20 years or so. Included is the only photo of the original stair case from Edith Tunis Sale's Colonial Interiors, published in 1930. Plaster has been removed, nail holes documented and analyzed, plaster ghosts discussed, and the reason a stud has been flipped and rotated has been debated. Basically, what I am trying to say is we are going to great lengths to make sure the restored stair passage is as historically accurate as the evidence will allow. No nail hole will go unanalyzed.